Barapullah Phase 4 will connect South Delhi with IGI Airport

New Delhi: Because the Barapula elevated hall is deliberate to be prolonged from INA to Dhaula Kuan, within the subsequent fourth section of its development, the Delhi authorities needs to attach this elevated hall with INA on to the Indira Gandhi Worldwide (IGI) airport. This whole route shall be free from visitors indicators.

After completion of phases three and 4, the journey time between East Delhi to IGI airport shall be simply 40 minutes.

The third section of the Barapullah elevated mission was to be accomplished in October 2017. However attributable to steady delay the work remained incomplete. About 80 p.c work of connecting East Delhi with South Delhi has been carried out to date.

In keeping with PWD, social influence evaluation needs to be carried out earlier than any land is acquired. Because it was being studied for a number of years, there’s a delay within the completion of the mission. Soggy soil is alleged to be one other reason for developmental delay, because it makes it troublesome for the pillars to face.

Within the fourth section of Barapullah Elevated Street Undertaking, it’s believed that about 7 km shall be lined on the Ring Street. On this section, the hall shall be linked to INA, which is able to additional cowl Safdarjung Airport, Sarojini Nagar, Chanakyapuri, Dhaula Kuan and Delhi Cantonment Military Hospital.

The deadline for completion of all phases of the Barapullah Elevated Street mission was 2020.