BMRC floats tender for 318 rolling inventory coaches for Bangalore Metro Section 2 Metro Rail Immediately

[ad_1]

BMRC floats tender for 318 rolling stock coaches for Bangalore Metro Phase 2


Bengaluru, India (Metro Rail Immediately): Bangalore Metro Rail Company Restricted (BMRCL) has issued a young discover for procurement of 318 Metro Coaches (Rolling Inventory) for Section 2, 2A and 2B underneath building of Bangalore Metro Rail Venture.

The scope of labor contains design, fabrication, provide, set up, testing and commissioning of 318 nos. Coaching of personnel together with variety of commonplace gauge metro automobiles and in depth upkeep of as much as fifteen (15) years underneath Bangalore Metro Rail Venture Section-II, 2A and 2B.

For the primary time, BMRCL has additionally launched a brand new clause on upkeep of coaches. The producer/provider has to take care of the coaches of the Metro practice for a interval of 15 years underneath the defect legal responsibility interval.

vital data

  • Tender Discover No.: BMRCL / Section-II / Worldwide Aggressive Bidding (ICB) No. 5 RS-DM
  • Concern Date: 19 September 2022
  • Sale of Tender Paperwork: 30.09.2022 to fifteen.10.2022
  • Pre-Bid Assembly: 28.10.2022 at 11.00 AM
  • Final date for submission of bid: 12.12.2022 as much as 03.00 PM
  • Opening of Technical Bids: 12.12.2022 at 03.30 PM

As per the tender discover, 16 trainsets (96 coaches) might be used for companies on Kalena Agrahara to Nagawara line which has Dairy circle and 14 km underground part from Nagawara, 16 trainsets (96 coaches) for ORR metro line . CSB Junction to KR Puram, and the remaining 21 trains (126 coaches) might be used for airport line extension from KR Puram to Kempegowda Worldwide Airport terminal (Section 2B). The whole size of the hall is 55 km and is predicted to be operational by 2024-25.

“We now have taken a cue from the Delhi Metro. Presently, numerous assets are being spent on upkeep of coaches which incorporates periodic restore work, spare components and others. To save cash in the long term, different metros have additionally began implementing this situation whereas shopping for coaches,” stated Anjum Parvez, Managing Director, BMRCL. Hindu knowledgeable of.

“These will be operated with out drivers. Superior signaling techniques assist scale back headway in as little as 2 minutes. At current we’re operating trains for at the very least 5 minutes. The practice could have superior techniques that additionally verify the well being of the monitor and obstructions. For the trains plying until the airport, in the course of the design part, we’re planning to supply baggage storage for air passengers and different amenities,” he stated.

On the standing of buy of metro coaches from China Railway Rolling Inventory Company of China, which was contracted to produce 216 coaches to BMRCL, Parvez stated, “CRRC has entered into an MoU with an Indian firm for manufacturing of coaches. has entered. We’re trying ahead to receiving these new coaches early subsequent yr. These coaches might be operated on RV Highway – Bommasandra line.

For fast updates, please observe Metro Rail Immediately Google Information,